By
A. Ranjan
and B. K. Das |
Abstract
The expansion programme under taken to
make Tata Steel a 5.0 mtpa integrated steel plant emphasised expansion
of sinter making facility from 3.8 mtpa to 5.8 mtpa. A 2.0 mtpa
state-of-the-art sinter making facility, sinter plant No.3, has been
commissioned. It has a modern bedding and blending plant and embodies
all the recently developed features in the sinter making technology. The
commissioning trial was started in February 2005. The quality of the
initial product is better than the specified parameters of performance.
The performance achieved so far indicates it will be able to achieve its
rated capacity in first year of its commissioning. Present paper
documents the early performance indications, commissioning experiences
along with salient features and specifications of the plant and
machineries.
Introduction
The sinter making at
Tata Steel is now over four and half decades old. First three decades
with one plant, next one and half decades with two plants and now a
third plant. It was started with the start of 1.2 mtpa plant in 1959. A
second 1.37 mtpa capacity plant was added in 1989. The third plant is
associated with its expansion programme. The very attractive trend and
forecast of the steel demand in the domestic and global scenario
prompted the Tata Steel for its expansion programme in 2003. Expansion
is global. Now it will be a multi location, multi national steel plant.
It includes green field plants at BanglaDesh, Kalingnagar (Orissa,
India), Chattishgarh (India), Tantuposi (Jharkhand, India) and expansion
at Jamshedpur. At Jamshedpur, the expansion programme is in two phases (i)
1.0 million tonne expansion programme making Tata Steel a 5.0 mtpa plant
and a further (ii) 2.0 million tonne growth plan augmenting the capacity
to 7.0 mpta. The 1.0 mtpa expansion programme was undertaken during
2003-2004. The objective of this programme was to increase the steel
plant capacity from 4.0 mtpa to 5.0 mtpa and thus the full utilization
of steelmaking and further downstream facilities. This is to be achieved
without putting up new blast furnace or coke making facility. After
completion of 1.0 mtpa expansion the 2.0 mtpa expansion project known as
‘growth plan’ shall be undertaken.
|