  | 
     
       
       | 
      | 
     
    
      Phases of Modernisation 
        
       1980-84 
      Modernisation Phase I 
      
        -  The plans were
          implemented in a record
          time of 29 months.
 
        -  Two 130 tonnes LD
          converters were set up
          for the first time in an
          integrated steel plant in
          India.
 
        -  A four-hammer Bar
          Forging Machine (18,000
          tonnes capacity p.a.) was
          also installed. 
 
       
        
       1985-89 
      Modernisation Phase II 
      
        -  A Bar and Rod mill – the first of its
          kind in India - of a single strand high
 
        speed mill was set up. 
        -  In-house R & D efforts developed
          a new technology permitting the
          use of blue dust that improved the
        productivity of the blast furnaces.
 
        -  Coke Ovens using environment
          friendly stamp-charging technology
 
        were introduced. 
        -  Cost effective technology of coal
          injection in blast furnaces was
          implemented.
 
       
        
       1990-94 
      Modernisation Phase III 
      - The highly automated G blast
        furnace was installed with special
        charging and distribution system.
 
        -  LD Shop 2 with 130 tonne capacity
        LD vessels was set up.
 
        -  Two single stranded slab casters
        were installed.
 
        -  A semi-continuous Hot Strip Mill
          was introduced.
 
       
        
       1995-1999 
      Modernisation Phase IV 
      -  The hot metal capacity was raised to
        3 million tonnes per annum, crude steel
 
        capacity to 3.5 mtpa and saleable steel
        capacity to 3.2 mtpa. 
        -  One ladle furnace each was added to LD1
        and LD2.
 
        -  The 3rd single strand slab caster and 3rd
        converter were installed.
 
        -  Continuous Casting was increased to 95%
        from 65%.
 
        -  The Hot Strip Mill capacity doubled to 2
          million tonnes.
 
       
        
       2000-2005 
      Modernisation Phase V 
      -  IT enabled processes through
        the implementation of the ERP
        driven SAP and Ban systems
        were introduced to break
        prevalent mindsets through
        Knowledge Management.
 
        -   The state-of-the-art Cold
          Rolling Mill (1.2 million tonnes)
          was inaugurated with output
          of 800,000 tonnes of cold rolled
          and annealed products and
          about 400,000 tonnes of cold
          rolled coated products.
 
       
        
              
      TOP       | 
      | 
      |