rit_cor.jpg (689 bytes)

Upgraded.............
                    'G' BLAST FURNACE

‘G’ Blast Furnace was commissioned in 1992 with an installed capacity of 1 million tonne per annum (MTPA) hot metal production. Over the years with various improvement measures, the production capacity of the furnace was brought upto 1.2 MTPA. It was blown down on 3rd December 2004 for massive upgradation work. During its 12 years of operation, the furnace produced 14 million tonnes hot metal. The upgradation work was undertaken to enhance the capacity of the furnace to 1.8 MTPA with an expected life of minimum 15 years with state-of-the-art technology including: copper and cast iron staves, high top pressure, automated stag granulation crane, furnace cooling with demineralised water, enhanced coal injection facilities, etc.

Upgraded 'G' Blast Furnace

Besides capacity enhancement, the upgraded ‘G’ Furnace has been equipped with a sophisticated monitoring and control system and an up-to-date automation system to enable the furnace to produce high quality hot metal at the lowest cost.

For achieving cost-effective upgradation, a critical study of the existing and proposed new facilities was made. A judicious balance between the old and new facilities was struck.

Something-Fig.-1.gif (9452 bytes)
Upgraded 'G' Blast
Furnace model

To minimise the shutdown period, a project monitoring system comparable with the world’s best practices was put in place. Substantial quantity of work was completed during the pre-shutdown period while the furnace was in operation. A highly dedicated, experienced and motivated work force from Projects, Works, Contractors and Consultants was engaged to fulfil this objective. Areas of concern were : safety hazards of BF gas, space constraint, working at heights, etc. The existing ‘G’ Furnace also did not have any provision for salamander tapping. A rigorous exercise was undertaken with the help of European and Russian experts to assess the salamander volume, deciding on the salamander tapping location and making provision for salamander tapping while the furnace was in operation. For this purpose, a mock trial was conducted to facilitate the equipment selection, etc. Certain exercises were undertaken before hand to gain confidence on successful salamander tapping.


New BF shell erection

For the first time in Tata Steel, the salamander was tapped with the wind on to reduce the tapping time and the residual amount of hot metal. The repair of the blast furnace stove burners was successfully performed in all the three stoves while keeping the stoves in hot condition. This was also the first such feat in India. An elaborate procedure for furnace blowing down was also established in consultation with all experts from SMS Demag and the operating personnel.

For the first time in Tata Steel, the burden level was lowered to the tuyere level before salamander tapping to accelerate the evacuation of the furnace after blowing down.

'G' Blast Furnace upgradation activities

After having gained experience during the ‘F’ Blast Furnace upgradation work, the knowledge of dismantling sequence for the furnace shell and erection was firmed up using a movable trolley for shifting of the shell assembly. Strand jacks at two different levels of supports were provided for the purpose, after ascertaining the adequacy of the existing tower structure.

This furnace with copper and cast iron staves, as well as well designed carbon hearth is the first of its kind in India and is poised to scale newer heights of excellence in the days to come.

   

Main features of the upgraded “G” BF

Target : 1,800,000 HM t/year (+36%)
Daily average : 5150 HM t/day
Working volume : 2300 m3 (+46%)
Hearth diameter : 11,05m
No. of tuyeres : 30
No. of tapholes : 2
   

Project data

Concrete, cum - 19000
Structural steel, tonnes - 5500
Shell, tonnes - 650
Refractory work, tonnes - 7300
Equipment, tonnes - 4600
Cable laying, km - 950
Piping work, km - 75
  

Major milestones

  

Improvements brought about

Placement of order for main package 10 Apr ’03 Parameters Before (1992-2004) After (2005)
Commencement of pre-shutdown work 1 Sep ’03 Furnace capacity, Mtpa 1.2 1.8
Delivery of imported equipment April ’04 Working volume, cum 1581 2308
Delivery of BF shell from TGS Mar ’04 - May ’04 Furnace campaign life, years 13 15 at least
Pre-assembly of BF shell by L&T Apr ’04-Aug ’04 High top pressure, bar g 1.25 1.5
Furnace blow out 3Dec ’04 Tuyere, nos 22 30
Salamander tapping 3Dec ’04 No. of cast house 1 2
Furnace shell dismantling 6Dec ’04 - 3 Jan ’05 Taphole angle, deg. 72 132
Erection of BF shell 5Jan ’05 - 18 Jan ’05
Refractory work 23 Jan ’05 - 6 Mar ’05
Cold and sequential trials 7Mar ’05 - 22Mar ’05
Furnace filling 22 Mar ’05
Blow-in 6th April ’05

 

Main changes

Extension of cooled wall area

  • Replacement of existing cooling boxes with cast iron staves to have thinner walls and avoid dome shell replacement
  • Provision of entirely cooled shaft up to throat armour area to better sustain the increased heat loads resulting from higher PCI operation
  • Tuyere zone stave cooling+carbon block lining

Installation of copper staves in the critical area

  • Hot rolled copper staves (SMS Demag design)
  • Largely tested equipment as a key component to ensure long campaigns

Hearth geometry/materials quality upgrade

  • Super-micropore carbon blocks in the elephant foot and taphole area
  • Micropore carbon blocks in the lateral walls
  • Minimisation of the number of joints by large blocks installation.