rit_cor.jpg (689 bytes)

TABLE 1 : FEATURES OF LD1 AND LD2 SHOPS OF TATA STEEL

Sl. No. Parameters LD1 shop LD2 shop
1. Year of Installation 1983 1994
2. Crude Steel Capacity 1.3 mtpa cast billets* 2.7 mtpa cast slabs
3. Actual Production(02-03) 1.23 mtpa cast billets and 0.07 mtpa cast ingots 2.8 mtpa cast slabs
4. Hot Metal Pretreatment One De-S station Two De-S stations
5. Hot Metal Handling Open-top ladles/mixer for storage Torpedo cars
6. LD Vessels Two (1/2 vessel operations) Three ( 2/3 vessel             operations)
7. Heat Size 130 tonnes 127 tonnes (original)
136 tonnes (current)
8. Specific Volume ~1.1m3/tonne ~1.1m3/tonne
9. Secondary Steelmaking Facilities On-line tap purging station attached to each vessel
One Ladle Furnace
One VADR unit
On-line purging station attached to each vessel
Two Ladle Furnaces
One RH-Degasser
10. Casters Two-six-strand billet casters (100, 127, 130 mm sq billets) Three-single-strand curved mould slab casters
11. Casting speed                     3m/min (avg) for CC1
2.65 m/min (avg) for CC2
1.02 m/min (average)
12. Vessel Life (No. of heats per campaign) ~1635 heats average FY-03) with tar dolo (and zoning with MgO-C) ~1500 heats average with tar dolo (and zoning with MgO-C)
13. Ladle Life (No. of heats/lining) 70.7 (FY-03) ~83 (FY-03)
14. Heats/day 27.5 (average FY-03)
43 (maximum)
56 (annual average)
68 (maximum)
*Note : Ingot casting eliminated from April 2003

 

TABLE 2 : HOT METAL BALANCE -- CURRENT AND FUTURE
AFTER 1.0 MILLION TONNE EXPANSION

Hot Metal Current (BASE) After 1 mtpa
  Expansion
“A” to “F” Furnaces 3.20 mtpa 3.50 mtpa
“G” Furnace 1.20 mtpa 1.80 mtpa
Total 4.40 mtpa 5.30 mtpa

For the increased hot metal requirement, it was considered necessary to enhance capacity of G Blast Furnace by ~50% to 1.8 mtpa. Additionally, with improvements in ironmaking process, an increase of 0.3 mtpa of hot metal was also anticipated at the older A-F furnaces. Thus, the total hot metal capacity was set at ~5.3 mtpa as shown in Table 2, to meet the additional requirement for the 1.0 mtpa expansion of crude steel production.

At the moment, hot metal is supplied to LD 1 in open-top ladles while LD 2 gets all its supply in 220 tonne torpedos. After the 1.0 mtpa expansion, LD 1 shop will also receive hot metal in torpedos.

The key parameters of hot metal are expected to be as follows :

  • Sulphur 0.070% (same as now)

  • Phosphorus 0.250% (same as now)

  • Silicon 0.80% (lower than current)

  • Temperature 13400C (marginally higher than current)

It is expected that variability in hot metal composition would improve as compared to the current scenario.


Increasing Crude Steel Production - Basic Issues


The basic enablers that are normally to be adopted for increasing crude steel production at any steelmelting shop are as follows and the same are applicable to the two steelmelting shops of Tata Steel :

  • Increase heat size

  • Increase number of heats tapped / cast

  • Increase casting speed